The line included the entire power plant auxiliaries including switch gear, transformers, HRSG’s, steam turbines etc. except for below mentioned components.

360 Turbine
Equipment subject to Scope:-

Heat Recovery Steam Generators

Also included is the entire power plant auxiliaries including switch gear, transformers, HRSG’s, steam turbines etc. except for below mentioned components.
N.B. Not included in the scope :-
A. Cooling towers
B. Civil buildings
C. Water Demineralisation Plant
D. Feed water pumps to plant
Executive Summary:
The turbines have low fired hours as follow: GT1……………44,230 hours
GT2……………46,505 hours
GT3……………31,583 hours
Total starts are as follows: GT1……………163 starts
GT2……………193 starts
GT3……………132 starts
The hot path history is as follows:
GT1…………… 20,455 hours – after first repaired
GT2…………… 350 hours after first major inspection - new hot parts fitted
GT3…………… 6,600 hours after first major inspection – new hot parts fitted
At the last inspection of phase two (GT1 & GT2) the plant was exceeding the ISO heat, this demonstrates that the plant has been maintained to an exceptional standard. Phase 1 is heat against the ISO.